Where can I put a micro fulfillment center in Arlington County, VA?

“micro fulfillment center” matches 2 uses this ordinance names separately. We do not choose between them — they can have different answers, so every one is shown.

Micro-fulfillment center

Allowed by right in 7 districts

DistrictProperties loadedCodeWhat says so
C-1
the use table's own cell
51PSec. 7.1.2
Read from the use table: Table 7.1.2 on PDF page 89, row "Micro-fulfillment center", column "C-1", reads "P" (P = Permitted by-right).
C-2
the use table's own cell
266PSec. 7.1.2
Read from the use table: Table 7.1.2 on PDF page 89, row "Micro-fulfillment center", column "C-2", reads "P" (P = Permitted by-right).
C-3
the use table's own cell
84PSec. 7.1.2
Read from the use table: Table 7.1.2 on PDF page 89, row "Micro-fulfillment center", column "C-3", reads "P" (P = Permitted by-right).
C-O-A
the use table's own cell
35PSec. 7.1.2
Read from the use table: Table 7.1.2 on PDF page 89, row "Micro-fulfillment center", column "C-O-A", reads "P" (P = Permitted by-right).
C-R
the use table's own cell
16PSec. 7.1.2
Read from the use table: Table 7.1.2 on PDF page 89, row "Micro-fulfillment center", column "C-R", reads "P" (P = Permitted by-right).
C-TH
the use table's own cell
no parcels loadedPSec. 7.1.2
Read from the use table: Table 7.1.2 on PDF page 89, row "Micro-fulfillment center", column "C-TH", reads "P" (P = Permitted by-right).
MU-VS
the use table's own cell
2PSec. 7.1.2
Read from the use table: Table 7.1.2 on PDF page 89, row "Micro-fulfillment center", column "MU-VS", reads "P" (P = Permitted by-right).

Allowed only with a discretionary approval in 9 districts

These require a hearing or an approval from the county. They are not a “no”, and they are not a “yes” either.

DistrictProperties loadedCodeWhat says so
C-O
the use table's own cell
106SSec. 7.1.2
Read from the use table: Table 7.1.2 on PDF page 89, row "Micro-fulfillment center", column "C-O", reads "S" (S = Special exception -- requires site plan approval (Sec. 15.5)).
C-O CRYSTAL CITY
the use table's own cell
no parcels loadedSSec. 7.1.2
Read from the use table: Table 7.1.2 on PDF page 89, row "Micro-fulfillment center", column "C-O CRYSTAL CITY", reads "S" (S = Special exception -- requires site plan approval (Sec. 15.5)).
C-O ROSSLYN
the use table's own cell
no parcels loadedSSec. 7.1.2
Read from the use table: Table 7.1.2 on PDF page 89, row "Micro-fulfillment center", column "C-O ROSSLYN", reads "S" (S = Special exception -- requires site plan approval (Sec. 15.5)).
C-O-1.0
the use table's own cell
150SSec. 7.1.2
Read from the use table: Table 7.1.2 on PDF page 89, row "Micro-fulfillment center", column "C-O-1.0", reads "S" (S = Special exception -- requires site plan approval (Sec. 15.5)).
C-O-1.5
the use table's own cell
145SSec. 7.1.2
Read from the use table: Table 7.1.2 on PDF page 89, row "Micro-fulfillment center", column "C-O-1.5", reads "S" (S = Special exception -- requires site plan approval (Sec. 15.5)).
C-O-2.5
the use table's own cell
74SSec. 7.1.2
Read from the use table: Table 7.1.2 on PDF page 89, row "Micro-fulfillment center", column "C-O-2.5", reads "S" (S = Special exception -- requires site plan approval (Sec. 15.5)).
R-C
the use table's own cell
79SSec. 7.1.2
Read from the use table: Table 7.1.2 on PDF page 89, row "Micro-fulfillment center", column "R-C", reads "S" (S = Special exception -- requires site plan approval (Sec. 15.5)).
RA-H-3.2
the use table's own cell
97SSec. 7.1.2
Read from the use table: Table 7.1.2 on PDF page 89, row "Micro-fulfillment center", column "RA-H-3.2", reads "S" (S = Special exception -- requires site plan approval (Sec. 15.5)).
RA4.8
the use table's own cell
48SSec. 7.1.2
Read from the use table: Table 7.1.2 on PDF page 89, row "Micro-fulfillment center", column "RA4.8", reads "S" (S = Special exception -- requires site plan approval (Sec. 15.5)).

Micro-fulfillment centers

Allowed by right in 4 districts

DistrictProperties loadedCodeWhat says so
CM
the use table's own cell
30PSec. 8.1.2
Read from the use table: Table 8.1.2 on PDF page 159, row "Micro-fulfillment centers", column "CM", reads "P" (P = Permitted by-right).
CP-FBC
the use table's own cell
10PSec. 11.1.5
Read from the use table: Table 11.1.5 on PDF page 212, row "Micro-fulfillment centers", column "CP-FBC", reads "P" (P = Permitted by-right).
M-1
the use table's own cell
42PSec. 8.1.2
Read from the use table: Table 8.1.2 on PDF page 159, row "Micro-fulfillment centers", column "M-1", reads "P" (P = Permitted by-right).
M-2
the use table's own cell
2PSec. 8.1.2
Read from the use table: Table 8.1.2 on PDF page 159, row "Micro-fulfillment centers", column "M-2", reads "P" (P = Permitted by-right).

Pro and reports for Arlington County, VA are coming soon.

Notify me when Arlington County, VA launches

We use this email only to tell you when Arlington County, VA launches. We never share it.

This answer is good through June 13, 2026 — that is the date the ordinance we hold runs to, as published by Arlington County. We last checked with the county on September 14, 2026 and found nothing newer. That is a check on that date, not a promise about today.

What this does not cover

Built from scripts/build_reverse_index.py, generated 2026-10-11T20:59:04+00:00.