Construction Site Office and Storage

It depends in 36 districts

DistrictProperties loadedCodeWhat says so
C-1 Varies
Depends: administrative permit, only if the use is a type or location that Sec. 4102.8.C(2) allows here and the use stays within the limits in Sec. 4102.8.C(1)
when the use is a type or location that Sec. 4102.8.C(2) allows here
Sec. 4102.8.C(2), Sec. 4102.8.C(1): The use must be located within the recorded subdivision that it serves or on the same lot where the construction project is located. … An administrative permit may be issued for a period beginning no earlier than 30 days before the commencement of actual construction and terminating no later than 20 days after completion of the last building to be constructed in the project.
94
no ZIP in the county's record (5), 22003 (50), 22015 (37), 22044 (2)
APSec. 4101
Read from the use table: Table 4101.1, row "Construction Site Office and Storage", column "C-1", reads "AP". Sec. 4101.1 says: G. An “AP” in a cell of Table 4101.1 or Table 4101.2 indicates that the use is allowed only with approval of an administrative permit by the Zoning Administrator.
C-2 Varies
Depends: administrative permit, only if the use is a type or location that Sec. 4102.8.C(2) allows here and the use stays within the limits in Sec. 4102.8.C(1)
when the use is a type or location that Sec. 4102.8.C(2) allows here
Sec. 4102.8.C(2), Sec. 4102.8.C(1): The use must be located within the recorded subdivision that it serves or on the same lot where the construction project is located. … An administrative permit may be issued for a period beginning no earlier than 30 days before the commencement of actual construction and terminating no later than 20 days after completion of the last building to be constructed in the project.
1,255
no ZIP in the county's record (20), 20120 (3), 20121 (4), 22003 (189), 22015 (120), 22027 (10), 22030 (1), 22031 (12), 22032 (38), 22041 (88), 22042 (2), 22043 (15), 22044 (85), 22066 (1), 22101 (54), 22124 (38), 22150 (5), 22151 (57), 22152 (63), 22153 (3), 22181 (12), 22182 (62), 22302 (19), 22303 (1), 22306 (35), 22307 (57), 22308 (2), 22309 (3), 22310 (188), 22312 (68)
APSec. 4101
Read from the use table: Table 4101.1, row "Construction Site Office and Storage", column "C-2", reads "AP". Sec. 4101.1 says: G. An “AP” in a cell of Table 4101.1 or Table 4101.2 indicates that the use is allowed only with approval of an administrative permit by the Zoning Administrator.
C-3 Varies
Depends: administrative permit, only if the use is a type or location that Sec. 4102.8.C(2) allows here and the use stays within the limits in Sec. 4102.8.C(1)
when the use is a type or location that Sec. 4102.8.C(2) allows here
Sec. 4102.8.C(2), Sec. 4102.8.C(1): The use must be located within the recorded subdivision that it serves or on the same lot where the construction project is located. … An administrative permit may be issued for a period beginning no earlier than 30 days before the commencement of actual construction and terminating no later than 20 days after completion of the last building to be constructed in the project.
730
no ZIP in the county's record (45), 20121 (3), 20170 (1), 20171 (3), 20191 (3), 22003 (286), 22030 (2), 22031 (71), 22033 (2), 22041 (4), 22042 (45), 22043 (98), 22044 (6), 22046 (1), 22079 (1), 22101 (10), 22102 (16), 22150 (8), 22182 (77), 22302 (1), 22303 (2), 22306 (1), 22307 (4), 22309 (1), 22310 (30), 22312 (9)
APSec. 4101
Read from the use table: Table 4101.1, row "Construction Site Office and Storage", column "C-3", reads "AP". Sec. 4101.1 says: G. An “AP” in a cell of Table 4101.1 or Table 4101.2 indicates that the use is allowed only with approval of an administrative permit by the Zoning Administrator.
C-4 Varies
Depends: administrative permit, only if the use is a type or location that Sec. 4102.8.C(2) allows here and the use stays within the limits in Sec. 4102.8.C(1)
when the use is a type or location that Sec. 4102.8.C(2) allows here
Sec. 4102.8.C(2), Sec. 4102.8.C(1): The use must be located within the recorded subdivision that it serves or on the same lot where the construction project is located. … An administrative permit may be issued for a period beginning no earlier than 30 days before the commencement of actual construction and terminating no later than 20 days after completion of the last building to be constructed in the project.
73
no ZIP in the county's record (13), 22003 (1), 22030 (19), 22041 (2), 22042 (3), 22043 (1), 22102 (21), 22150 (5), 22182 (8)
APSec. 4101
Read from the use table: Table 4101.1, row "Construction Site Office and Storage", column "C-4", reads "AP". Sec. 4101.1 says: G. An “AP” in a cell of Table 4101.1 or Table 4101.2 indicates that the use is allowed only with approval of an administrative permit by the Zoning Administrator.
C-5 Varies
Depends: administrative permit, only if the use is a type or location that Sec. 4102.8.C(2) allows here and the use stays within the limits in Sec. 4102.8.C(1)
when the use is a type or location that Sec. 4102.8.C(2) allows here
Sec. 4102.8.C(2), Sec. 4102.8.C(1): The use must be located within the recorded subdivision that it serves or on the same lot where the construction project is located. … An administrative permit may be issued for a period beginning no earlier than 30 days before the commencement of actual construction and terminating no later than 20 days after completion of the last building to be constructed in the project.
476
no ZIP in the county's record (43), 20170 (1), 20171 (2), 20191 (1), 22003 (18), 22015 (2), 22027 (2), 22030 (1), 22031 (24), 22033 (1), 22039 (5), 22041 (19), 22042 (26), 22043 (6), 22044 (2), 22046 (1), 22066 (1), 22079 (9), 22101 (29), 22102 (7), 22124 (15), 22150 (11), 22151 (1), 22180 (3), 22182 (24), 22303 (108), 22306 (27), 22307 (3), 22308 (7), 22309 (41), 22310 (17), 22312 (14), 22315 (5)
APSec. 4101
Read from the use table: Table 4101.1, row "Construction Site Office and Storage", column "C-5", reads "AP". Sec. 4101.1 says: G. An “AP” in a cell of Table 4101.1 or Table 4101.2 indicates that the use is allowed only with approval of an administrative permit by the Zoning Administrator.
C-6 Varies
Depends: administrative permit, only if the use is a type or location that Sec. 4102.8.C(2) allows here and the use stays within the limits in Sec. 4102.8.C(1)
when the use is a type or location that Sec. 4102.8.C(2) allows here
Sec. 4102.8.C(2), Sec. 4102.8.C(1): The use must be located within the recorded subdivision that it serves or on the same lot where the construction project is located. … An administrative permit may be issued for a period beginning no earlier than 30 days before the commencement of actual construction and terminating no later than 20 days after completion of the last building to be constructed in the project.
697
no ZIP in the county's record (73), 20120 (2), 20121 (39), 20124 (6), 20151 (21), 20170 (5), 20171 (11), 22003 (88), 22015 (7), 22027 (5), 22030 (8), 22031 (45), 22032 (2), 22033 (4), 22039 (1), 22041 (83), 22042 (13), 22043 (1), 22044 (1), 22066 (24), 22079 (12), 22101 (69), 22102 (3), 22106 (1), 22150 (87), 22151 (4), 22152 (10), 22153 (5), 22180 (1), 22182 (8), 22303 (6), 22306 (16), 22307 (4), 22308 (1), 22309 (4), 22310 (9), 22312 (17), 22315 (1)
APSec. 4101
Read from the use table: Table 4101.1, row "Construction Site Office and Storage", column "C-6", reads "AP". Sec. 4101.1 says: G. An “AP” in a cell of Table 4101.1 or Table 4101.2 indicates that the use is allowed only with approval of an administrative permit by the Zoning Administrator.
C-7 Varies
Depends: administrative permit, only if the use is a type or location that Sec. 4102.8.C(2) allows here and the use stays within the limits in Sec. 4102.8.C(1)
when the use is a type or location that Sec. 4102.8.C(2) allows here
Sec. 4102.8.C(2), Sec. 4102.8.C(1): The use must be located within the recorded subdivision that it serves or on the same lot where the construction project is located. … An administrative permit may be issued for a period beginning no earlier than 30 days before the commencement of actual construction and terminating no later than 20 days after completion of the last building to be constructed in the project.
105
no ZIP in the county's record (24), 20120 (2), 20121 (3), 22003 (1), 22033 (10), 22044 (12), 22102 (9), 22150 (13), 22182 (31)
APSec. 4101
Read from the use table: Table 4101.1, row "Construction Site Office and Storage", column "C-7", reads "AP". Sec. 4101.1 says: G. An “AP” in a cell of Table 4101.1 or Table 4101.2 indicates that the use is allowed only with approval of an administrative permit by the Zoning Administrator.
C-8 Varies
Depends: administrative permit, only if the use is a type or location that Sec. 4102.8.C(2) allows here and the use stays within the limits in Sec. 4102.8.C(1)
when the use is a type or location that Sec. 4102.8.C(2) allows here
Sec. 4102.8.C(2), Sec. 4102.8.C(1): The use must be located within the recorded subdivision that it serves or on the same lot where the construction project is located. … An administrative permit may be issued for a period beginning no earlier than 30 days before the commencement of actual construction and terminating no later than 20 days after completion of the last building to be constructed in the project.
1,213
no ZIP in the county's record (118), 20120 (32), 20121 (10), 20124 (1), 20151 (46), 20164 (1), 20170 (9), 20171 (4), 20190 (1), 22003 (41), 22030 (16), 22031 (16), 22033 (2), 22039 (1), 22041 (73), 22042 (135), 22043 (12), 22044 (13), 22046 (29), 22060 (3), 22066 (102), 22079 (21), 22101 (40), 22102 (7), 22124 (2), 22150 (21), 22151 (2), 22181 (3), 22182 (14), 22302 (2), 22303 (46), 22306 (121), 22307 (2), 22309 (223), 22310 (8), 22312 (36)
APSec. 4101
Read from the use table: Table 4101.1, row "Construction Site Office and Storage", column "C-8", reads "AP". Sec. 4101.1 says: G. An “AP” in a cell of Table 4101.1 or Table 4101.2 indicates that the use is allowed only with approval of an administrative permit by the Zoning Administrator.
I-2 Varies
Depends: administrative permit, only if the use is a type or location that Sec. 4102.8.C(2) allows here and the use stays within the limits in Sec. 4102.8.C(1)
when the use is a type or location that Sec. 4102.8.C(2) allows here
Sec. 4102.8.C(2), Sec. 4102.8.C(1): The use must be located within the recorded subdivision that it serves or on the same lot where the construction project is located. … An administrative permit may be issued for a period beginning no earlier than 30 days before the commencement of actual construction and terminating no later than 20 days after completion of the last building to be constructed in the project.
5
no ZIP in the county's record (2), 20171 (1), 20191 (2)
APSec. 4101
Read from the use table: Table 4101.1, row "Construction Site Office and Storage", column "I-2", reads "AP". Sec. 4101.1 says: G. An “AP” in a cell of Table 4101.1 or Table 4101.2 indicates that the use is allowed only with approval of an administrative permit by the Zoning Administrator.
I-3 Varies
Depends: administrative permit, only if the use is a type or location that Sec. 4102.8.C(2) allows here and the use stays within the limits in Sec. 4102.8.C(1)
when the use is a type or location that Sec. 4102.8.C(2) allows here
Sec. 4102.8.C(2), Sec. 4102.8.C(1): The use must be located within the recorded subdivision that it serves or on the same lot where the construction project is located. … An administrative permit may be issued for a period beginning no earlier than 30 days before the commencement of actual construction and terminating no later than 20 days after completion of the last building to be constructed in the project.
274
no ZIP in the county's record (26), 20151 (131), 20190 (5), 20191 (75), 22015 (2), 22041 (2), 22042 (2), 22102 (22), 22150 (7), 22182 (2)
APSec. 4101
Read from the use table: Table 4101.1, row "Construction Site Office and Storage", column "I-3", reads "AP". Sec. 4101.1 says: G. An “AP” in a cell of Table 4101.1 or Table 4101.2 indicates that the use is allowed only with approval of an administrative permit by the Zoning Administrator.
I-4 Varies
Depends: administrative permit, only if the use is a type or location that Sec. 4102.8.C(2) allows here and the use stays within the limits in Sec. 4102.8.C(1)
when the use is a type or location that Sec. 4102.8.C(2) allows here
Sec. 4102.8.C(2), Sec. 4102.8.C(1): The use must be located within the recorded subdivision that it serves or on the same lot where the construction project is located. … An administrative permit may be issued for a period beginning no earlier than 30 days before the commencement of actual construction and terminating no later than 20 days after completion of the last building to be constructed in the project.
475
no ZIP in the county's record (38), 20151 (108), 20170 (2), 20171 (16), 20190 (14), 20191 (55), 20196 (1), 22030 (3), 22031 (40), 22042 (3), 22043 (1), 22079 (65), 22102 (3), 22150 (5), 22151 (11), 22152 (6), 22160 (1), 22182 (83), 22310 (13), 22312 (3), 22315 (4)
APSec. 4101
Read from the use table: Table 4101.1, row "Construction Site Office and Storage", column "I-4", reads "AP". Sec. 4101.1 says: G. An “AP” in a cell of Table 4101.1 or Table 4101.2 indicates that the use is allowed only with approval of an administrative permit by the Zoning Administrator.
I-5 Varies
Depends: administrative permit, only if the use is a type or location that Sec. 4102.8.C(2) allows here and the use stays within the limits in Sec. 4102.8.C(1)
when the use is a type or location that Sec. 4102.8.C(2) allows here
Sec. 4102.8.C(2), Sec. 4102.8.C(1): The use must be located within the recorded subdivision that it serves or on the same lot where the construction project is located. … An administrative permit may be issued for a period beginning no earlier than 30 days before the commencement of actual construction and terminating no later than 20 days after completion of the last building to be constructed in the project.
1,876
no ZIP in the county's record (147), 20121 (142), 20151 (423), 20153 (1), 20171 (58), 20190 (67), 20191 (3), 22015 (28), 22030 (54), 22031 (134), 22032 (4), 22039 (4), 22042 (29), 22043 (23), 22046 (4), 22079 (214), 22082 (1), 22102 (35), 22150 (61), 22151 (63), 22153 (177), 22161 (1), 22180 (2), 22182 (47), 22303 (2), 22310 (36), 22312 (116)
APSec. 4101
Read from the use table: Table 4101.1, row "Construction Site Office and Storage", column "I-5", reads "AP". Sec. 4101.1 says: G. An “AP” in a cell of Table 4101.1 or Table 4101.2 indicates that the use is allowed only with approval of an administrative permit by the Zoning Administrator.
I-6 Varies
Depends: administrative permit, only if the use is a type or location that Sec. 4102.8.C(2) allows here and the use stays within the limits in Sec. 4102.8.C(1)
when the use is a type or location that Sec. 4102.8.C(2) allows here
Sec. 4102.8.C(2), Sec. 4102.8.C(1): The use must be located within the recorded subdivision that it serves or on the same lot where the construction project is located. … An administrative permit may be issued for a period beginning no earlier than 30 days before the commencement of actual construction and terminating no later than 20 days after completion of the last building to be constructed in the project.
187
no ZIP in the county's record (31), 20120 (3), 20151 (1), 22015 (1), 22046 (2), 22079 (104), 22150 (2), 22151 (23), 22159 (1), 22304 (7), 22312 (12)
APSec. 4101
Read from the use table: Table 4101.1, row "Construction Site Office and Storage", column "I-6", reads "AP". Sec. 4101.1 says: G. An “AP” in a cell of Table 4101.1 or Table 4101.2 indicates that the use is allowed only with approval of an administrative permit by the Zoning Administrator.
PCC / Secondary Varies
Depends: administrative permit, only if the use is a type or location that Sec. 4102.8.C(2) allows here and the use stays within the limits in Sec. 4102.8.C(1)
when the use is a type or location that Sec. 4102.8.C(2) allows here
Sec. 4102.8.C(2), Sec. 4102.8.C(1): The use must be located within the recorded subdivision that it serves or on the same lot where the construction project is located. … An administrative permit may be issued for a period beginning no earlier than 30 days before the commencement of actual construction and terminating no later than 20 days after completion of the last building to be constructed in the project.
no parcels loadedAPSec. 4101
Read from the use table: Table 4101.2, row "Construction Site Office and Storage", column "PCC / Secondary", reads "AP". Sec. 4101.1 says: G. An “AP” in a cell of Table 4101.1 or Table 4101.2 indicates that the use is allowed only with approval of an administrative permit by the Zoning Administrator.
PDC / Secondary Varies
Depends: administrative permit, only if the use is a type or location that Sec. 4102.8.C(2) allows here and the use stays within the limits in Sec. 4102.8.C and Sec. 2105.4.C(1)
when the use is a type or location that Sec. 4102.8.C(2) allows here
Sec. 4102.8.C(2), Sec. 4102.8.C(1), Sec. 2105.4.C(1)(a), Sec. 2105.4.C(1)(b), Sec. 2105.4.C(1)(c), Sec. 2105.4.C(1)(d), Sec. 2105.4.C(1)(b)1, Sec. 2105.4.C(1)(b)2, Sec. 2105.4.C(1)(b)3: The use must be located within the recorded subdivision that it serves or on the same lot where the construction project is located. … An administrative permit may be issued for a period beginning no earlier than 30 days before the commencement of actual construction and terminating no later than 20 days after completion of the last building to be constructed in the project. … Secondary uses are only permitted in a PDC District containing one or more principal uses. … The gross floor area of all secondary uses may not exceed 75 percent of the total gross floor area in the development, unless modified by the Board to implement the Comprehensive Plan. … Secondary uses must be designed as an integrated component of the planned development and must be designed to maintain and protect the character of adjacent properties. … Except for accessory outdoor dining in accordance with subsection 4102.7.L, any outdoor component of a commercial use must be shown on the final development plan. … Balconies, porches, decks, breezeways, stoops, and stairs that may be covered but have at least one open side; and … Breezeways that may be covered but have two open ends. … For the purpose of this subsection (b), an open side or open end has no more than 50 percent of the total area between the side(s), roof, and floor enclosed with railings, walls, or architectural features.
no parcels loadedAPSec. 4101
Read from the use table: Table 4101.2, row "Construction Site Office and Storage", column "PDC / Secondary", reads "AP". Sec. 4101.1 says: G. An “AP” in a cell of Table 4101.1 or Table 4101.2 indicates that the use is allowed only with approval of an administrative permit by the Zoning Administrator.
PDH / Secondary Varies
Depends: administrative permit, only if the use is a type or location that Sec. 4102.8.C(2) allows here and the use stays within the limits in Sec. 4102.8.C(1)
when the use is a type or location that Sec. 4102.8.C(2) allows here
Sec. 4102.8.C(2), Sec. 4102.8.C(1): The use must be located within the recorded subdivision that it serves or on the same lot where the construction project is located. … An administrative permit may be issued for a period beginning no earlier than 30 days before the commencement of actual construction and terminating no later than 20 days after completion of the last building to be constructed in the project.
no parcels loadedAPSec. 4101
Read from the use table: Table 4101.2, row "Construction Site Office and Storage", column "PDH / Secondary", reads "AP". Sec. 4101.1 says: G. An “AP” in a cell of Table 4101.1 or Table 4101.2 indicates that the use is allowed only with approval of an administrative permit by the Zoning Administrator.
PRC / Convention/Conference Center Varies
Depends: administrative permit, only if the use is a type or location that Sec. 4102.8.C(2) allows here and the use stays within the limits in Sec. 4102.8.C(1)
when the use is a type or location that Sec. 4102.8.C(2) allows here
Sec. 4102.8.C(2), Sec. 4102.8.C(1): The use must be located within the recorded subdivision that it serves or on the same lot where the construction project is located. … An administrative permit may be issued for a period beginning no earlier than 30 days before the commencement of actual construction and terminating no later than 20 days after completion of the last building to be constructed in the project.
no parcels loadedAPSec. 4101
Read from the use table: Table 4101.2, row "Construction Site Office and Storage", column "PRC / Convention/Conference Center", reads "AP". Sec. 4101.1 says: G. An “AP” in a cell of Table 4101.1 or Table 4101.2 indicates that the use is allowed only with approval of an administrative permit by the Zoning Administrator.
PRC / Neighborhood Convenience Center Varies
Depends: administrative permit, only if the use is a type or location that Sec. 4102.8.C(2) allows here and the use stays within the limits in Sec. 4102.8.C(1)
when the use is a type or location that Sec. 4102.8.C(2) allows here
Sec. 4102.8.C(2), Sec. 4102.8.C(1): The use must be located within the recorded subdivision that it serves or on the same lot where the construction project is located. … An administrative permit may be issued for a period beginning no earlier than 30 days before the commencement of actual construction and terminating no later than 20 days after completion of the last building to be constructed in the project.
no parcels loadedAPSec. 4101
Read from the use table: Table 4101.2, row "Construction Site Office and Storage", column "PRC / Neighborhood Convenience Center", reads "AP". Sec. 4101.1 says: G. An “AP” in a cell of Table 4101.1 or Table 4101.2 indicates that the use is allowed only with approval of an administrative permit by the Zoning Administrator.
PRC / Residential Varies
Depends: administrative permit, only if the use is a type or location that Sec. 4102.8.C(2) allows here and the use stays within the limits in Sec. 4102.8.C(1)
when the use is a type or location that Sec. 4102.8.C(2) allows here
Sec. 4102.8.C(2), Sec. 4102.8.C(1): The use must be located within the recorded subdivision that it serves or on the same lot where the construction project is located. … An administrative permit may be issued for a period beginning no earlier than 30 days before the commencement of actual construction and terminating no later than 20 days after completion of the last building to be constructed in the project.
no parcels loadedAPSec. 4101
Read from the use table: Table 4101.2, row "Construction Site Office and Storage", column "PRC / Residential", reads "AP". Sec. 4101.1 says: G. An “AP” in a cell of Table 4101.1 or Table 4101.2 indicates that the use is allowed only with approval of an administrative permit by the Zoning Administrator.
PRC / Town Center Varies
Depends: administrative permit, only if the use is a type or location that Sec. 4102.8.C(2) allows here and the use stays within the limits in Sec. 4102.8.C(1)
when the use is a type or location that Sec. 4102.8.C(2) allows here
Sec. 4102.8.C(2), Sec. 4102.8.C(1): The use must be located within the recorded subdivision that it serves or on the same lot where the construction project is located. … An administrative permit may be issued for a period beginning no earlier than 30 days before the commencement of actual construction and terminating no later than 20 days after completion of the last building to be constructed in the project.
no parcels loadedAPSec. 4101
Read from the use table: Table 4101.2, row "Construction Site Office and Storage", column "PRC / Town Center", reads "AP". Sec. 4101.1 says: G. An “AP” in a cell of Table 4101.1 or Table 4101.2 indicates that the use is allowed only with approval of an administrative permit by the Zoning Administrator.
PRC / Village Center Varies
Depends: administrative permit, only if the use is a type or location that Sec. 4102.8.C(2) allows here and the use stays within the limits in Sec. 4102.8.C(1)
when the use is a type or location that Sec. 4102.8.C(2) allows here
Sec. 4102.8.C(2), Sec. 4102.8.C(1): The use must be located within the recorded subdivision that it serves or on the same lot where the construction project is located. … An administrative permit may be issued for a period beginning no earlier than 30 days before the commencement of actual construction and terminating no later than 20 days after completion of the last building to be constructed in the project.
no parcels loadedAPSec. 4101
Read from the use table: Table 4101.2, row "Construction Site Office and Storage", column "PRC / Village Center", reads "AP". Sec. 4101.1 says: G. An “AP” in a cell of Table 4101.1 or Table 4101.2 indicates that the use is allowed only with approval of an administrative permit by the Zoning Administrator.
PRM / Secondary Varies
Depends: administrative permit, only if the use is a type or location that Sec. 4102.8.C(2) allows here and the use stays within the limits in Sec. 4102.8.C and Sec. 2105.5.C(2)
when the use is a type or location that Sec. 4102.8.C(2) allows here
Sec. 4102.8.C(2), Sec. 4102.8.C(1), Sec. 2105.5.C(2)(a), Sec. 2105.5.C(2)(b), Sec. 2105.5.C(2)(b)1, Sec. 2105.5.C(2)(b)2, Sec. 2105.5.C(2)(b)3: The use must be located within the recorded subdivision that it serves or on the same lot where the construction project is located. … An administrative permit may be issued for a period beginning no earlier than 30 days before the commencement of actual construction and terminating no later than 20 days after completion of the last building to be constructed in the project. … Secondary uses may be permitted only in a PRM District where at least 50 percent of the total gross floor area in the development is devoted to multifamily dwellings. … The floor area for dwellings will be determined in accordance with the gross floor area definition, except that the following features will not be deemed gross floor area: … Balconies, porches, decks, breezeways, stoops, and stairs that may be roofed but that have at least one open side; or … Breezeways that may be covered but that have two open ends. … For the purposes of this subsection, an open side or open end has no more than 50 percent of the total area between the side(s), roof, and floor enclosed with railings, walls, or architectural features.
no parcels loadedAPSec. 4101
Read from the use table: Table 4101.2, row "Construction Site Office and Storage", column "PRM / Secondary", reads "AP". Sec. 4101.1 says: G. An “AP” in a cell of Table 4101.1 or Table 4101.2 indicates that the use is allowed only with approval of an administrative permit by the Zoning Administrator.
PTC Varies
Depends: administrative permit, only if the use is a type or location that Sec. 4102.8.C(2) allows here and the use stays within the limits in Sec. 4102.8.C(1)
when the use is a type or location that Sec. 4102.8.C(2) allows here
Sec. 4102.8.C(2), Sec. 4102.8.C(1): The use must be located within the recorded subdivision that it serves or on the same lot where the construction project is located. … An administrative permit may be issued for a period beginning no earlier than 30 days before the commencement of actual construction and terminating no later than 20 days after completion of the last building to be constructed in the project.
533
no ZIP in the county's record (67), 22102 (432), 22182 (34)
APSec. 4101
Read from the use table: Table 4101.2, row "Construction Site Office and Storage", column "PTC", reads "AP". Sec. 4101.1 says: G. An “AP” in a cell of Table 4101.1 or Table 4101.2 indicates that the use is allowed only with approval of an administrative permit by the Zoning Administrator.
R-1 Varies
Depends: administrative permit, only if the use is a type or location that Sec. 4102.8.C(2) allows here and the use stays within the limits in Sec. 4102.8.C(1)
when the use is a type or location that Sec. 4102.8.C(2) allows here
Sec. 4102.8.C(2), Sec. 4102.8.C(1): The use must be located within the recorded subdivision that it serves or on the same lot where the construction project is located. … An administrative permit may be issued for a period beginning no earlier than 30 days before the commencement of actual construction and terminating no later than 20 days after completion of the last building to be constructed in the project.
26,110
no ZIP in the county's record (1,933), 20120 (98), 20121 (30), 20124 (80), 20151 (54), 20170 (711), 20171 (1,356), 20190 (27), 20191 (74), 20194 (237), 22003 (800), 22015 (434), 22027 (57), 22030 (566), 22031 (1,068), 22032 (475), 22033 (532), 22039 (1,063), 22042 (316), 22043 (110), 22044 (35), 22066 (2,705), 22079 (1,110), 22101 (1,579), 22102 (1,905), 22124 (3,260), 22150 (429), 22151 (1), 22152 (104), 22153 (197), 22180 (203), 22181 (892), 22182 (2,744), 22303 (1), 22306 (5), 22309 (6), 22310 (236), 22312 (55), 22315 (622)
APSec. 4101
Read from the use table: Table 4101.1, row "Construction Site Office and Storage", column "R-1", reads "AP". Sec. 4101.1 says: G. An “AP” in a cell of Table 4101.1 or Table 4101.2 indicates that the use is allowed only with approval of an administrative permit by the Zoning Administrator.
R-12 Varies
Depends: administrative permit, only if the use is a type or location that Sec. 4102.8.C(2) allows here and the use stays within the limits in Sec. 4102.8.C(1)
when the use is a type or location that Sec. 4102.8.C(2) allows here
Sec. 4102.8.C(2), Sec. 4102.8.C(1): The use must be located within the recorded subdivision that it serves or on the same lot where the construction project is located. … An administrative permit may be issued for a period beginning no earlier than 30 days before the commencement of actual construction and terminating no later than 20 days after completion of the last building to be constructed in the project.
7,817
no ZIP in the county's record (218), 20120 (143), 20151 (25), 20170 (38), 20171 (104), 22003 (1,310), 22015 (180), 22030 (86), 22031 (873), 22032 (257), 22041 (379), 22042 (125), 22043 (284), 22044 (26), 22079 (485), 22101 (22), 22124 (81), 22151 (32), 22152 (128), 22180 (166), 22181 (420), 22182 (618), 22304 (148), 22306 (445), 22307 (74), 22309 (135), 22310 (313), 22312 (702)
APSec. 4101
Read from the use table: Table 4101.1, row "Construction Site Office and Storage", column "R-12", reads "AP". Sec. 4101.1 says: G. An “AP” in a cell of Table 4101.1 or Table 4101.2 indicates that the use is allowed only with approval of an administrative permit by the Zoning Administrator.
R-16 Varies
Depends: administrative permit, only if the use is a type or location that Sec. 4102.8.C(2) allows here and the use stays within the limits in Sec. 4102.8.C(1)
when the use is a type or location that Sec. 4102.8.C(2) allows here
Sec. 4102.8.C(2), Sec. 4102.8.C(1): The use must be located within the recorded subdivision that it serves or on the same lot where the construction project is located. … An administrative permit may be issued for a period beginning no earlier than 30 days before the commencement of actual construction and terminating no later than 20 days after completion of the last building to be constructed in the project.
528
no ZIP in the county's record (8), 20121 (1), 22030 (2), 22041 (121), 22042 (48), 22043 (203), 22124 (18), 22309 (49), 22310 (78)
APSec. 4101
Read from the use table: Table 4101.1, row "Construction Site Office and Storage", column "R-16", reads "AP". Sec. 4101.1 says: G. An “AP” in a cell of Table 4101.1 or Table 4101.2 indicates that the use is allowed only with approval of an administrative permit by the Zoning Administrator.
R-2 Varies
Depends: administrative permit, only if the use is a type or location that Sec. 4102.8.C(2) allows here and the use stays within the limits in Sec. 4102.8.C(1)
when the use is a type or location that Sec. 4102.8.C(2) allows here
Sec. 4102.8.C(2), Sec. 4102.8.C(1): The use must be located within the recorded subdivision that it serves or on the same lot where the construction project is located. … An administrative permit may be issued for a period beginning no earlier than 30 days before the commencement of actual construction and terminating no later than 20 days after completion of the last building to be constructed in the project.
36,703
no ZIP in the county's record (1,416), 20120 (683), 20121 (75), 20124 (9), 20151 (537), 20170 (54), 20171 (1,832), 20191 (463), 20194 (16), 22003 (4,216), 22015 (172), 22027 (9), 22030 (1,195), 22031 (1,247), 22032 (4,060), 22033 (423), 22039 (61), 22041 (1,090), 22042 (475), 22043 (436), 22044 (753), 22066 (94), 22079 (25), 22101 (3,097), 22102 (778), 22124 (365), 22150 (376), 22151 (198), 22152 (1,145), 22153 (867), 22180 (118), 22181 (1,218), 22182 (1,733), 22207 (59), 22213 (2), 22306 (1,352), 22307 (459), 22308 (682), 22309 (3,310), 22310 (326), 22312 (1,274), 22315 (3)
APSec. 4101
Read from the use table: Table 4101.1, row "Construction Site Office and Storage", column "R-2", reads "AP". Sec. 4101.1 says: G. An “AP” in a cell of Table 4101.1 or Table 4101.2 indicates that the use is allowed only with approval of an administrative permit by the Zoning Administrator.
R-20 Varies
Depends: administrative permit, only if the use is a type or location that Sec. 4102.8.C(2) allows here and the use stays within the limits in Sec. 4102.8.C(1)
when the use is a type or location that Sec. 4102.8.C(2) allows here
Sec. 4102.8.C(2), Sec. 4102.8.C(1): The use must be located within the recorded subdivision that it serves or on the same lot where the construction project is located. … An administrative permit may be issued for a period beginning no earlier than 30 days before the commencement of actual construction and terminating no later than 20 days after completion of the last building to be constructed in the project.
17,328
no ZIP in the county's record (109), 20121 (812), 20151 (581), 20191 (169), 22003 (3,094), 22015 (303), 22030 (10), 22031 (577), 22032 (193), 22033 (262), 22041 (390), 22042 (706), 22043 (752), 22044 (63), 22046 (488), 22060 (1), 22079 (762), 22101 (35), 22102 (1,295), 22124 (778), 22150 (106), 22151 (1), 22152 (51), 22153 (1), 22180 (4), 22181 (277), 22182 (156), 22302 (31), 22303 (63), 22306 (915), 22307 (1,465), 22309 (2,420), 22310 (114), 22311 (106), 22312 (238)
APSec. 4101
Read from the use table: Table 4101.1, row "Construction Site Office and Storage", column "R-20", reads "AP". Sec. 4101.1 says: G. An “AP” in a cell of Table 4101.1 or Table 4101.2 indicates that the use is allowed only with approval of an administrative permit by the Zoning Administrator.
R-3 Varies
Depends: administrative permit, only if the use is a type or location that Sec. 4102.8.C(2) allows here and the use stays within the limits in Sec. 4102.8.C(1)
when the use is a type or location that Sec. 4102.8.C(2) allows here
Sec. 4102.8.C(2), Sec. 4102.8.C(1): The use must be located within the recorded subdivision that it serves or on the same lot where the construction project is located. … An administrative permit may be issued for a period beginning no earlier than 30 days before the commencement of actual construction and terminating no later than 20 days after completion of the last building to be constructed in the project.
68,283
no ZIP in the county's record (2,029), 20120 (2,083), 20121 (345), 20124 (1,773), 20151 (936), 20170 (3,100), 20171 (2,798), 20191 (408), 22003 (5,025), 22015 (4,194), 22027 (256), 22030 (520), 22031 (458), 22032 (2,172), 22033 (2,651), 22039 (45), 22041 (776), 22042 (1,009), 22043 (1,246), 22044 (913), 22046 (215), 22060 (20), 22079 (408), 22101 (4,663), 22102 (65), 22124 (53), 22150 (2,056), 22151 (4,441), 22152 (2,256), 22153 (3,759), 22180 (1,084), 22181 (346), 22182 (1,093), 22204 (17), 22206 (3), 22302 (22), 22303 (302), 22306 (1,421), 22307 (809), 22308 (4,263), 22309 (1,895), 22310 (3,852), 22311 (508), 22312 (1,102), 22315 (893)
APSec. 4101
Read from the use table: Table 4101.1, row "Construction Site Office and Storage", column "R-3", reads "AP". Sec. 4101.1 says: G. An “AP” in a cell of Table 4101.1 or Table 4101.2 indicates that the use is allowed only with approval of an administrative permit by the Zoning Administrator.
R-30 Varies
Depends: administrative permit, only if the use is a type or location that Sec. 4102.8.C(2) allows here and the use stays within the limits in Sec. 4102.8.C(1)
when the use is a type or location that Sec. 4102.8.C(2) allows here
Sec. 4102.8.C(2), Sec. 4102.8.C(1): The use must be located within the recorded subdivision that it serves or on the same lot where the construction project is located. … An administrative permit may be issued for a period beginning no earlier than 30 days before the commencement of actual construction and terminating no later than 20 days after completion of the last building to be constructed in the project.
6,428
no ZIP in the county's record (6), 20190 (44), 22041 (754), 22043 (252), 22044 (1,617), 22102 (2,497), 22180 (1), 22303 (1,224), 22306 (30), 22310 (2), 22312 (1)
APSec. 4101
Read from the use table: Table 4101.1, row "Construction Site Office and Storage", column "R-30", reads "AP". Sec. 4101.1 says: G. An “AP” in a cell of Table 4101.1 or Table 4101.2 indicates that the use is allowed only with approval of an administrative permit by the Zoning Administrator.
R-4 Varies
Depends: administrative permit, only if the use is a type or location that Sec. 4102.8.C(2) allows here and the use stays within the limits in Sec. 4102.8.C(1)
when the use is a type or location that Sec. 4102.8.C(2) allows here
Sec. 4102.8.C(2), Sec. 4102.8.C(1): The use must be located within the recorded subdivision that it serves or on the same lot where the construction project is located. … An administrative permit may be issued for a period beginning no earlier than 30 days before the commencement of actual construction and terminating no later than 20 days after completion of the last building to be constructed in the project.
16,986
no ZIP in the county's record (365), 22003 (787), 22027 (78), 22030 (4), 22031 (29), 22042 (4,980), 22043 (2,349), 22046 (1,265), 22079 (19), 22101 (301), 22124 (32), 22150 (1,788), 22151 (143), 22152 (38), 22180 (9), 22181 (63), 22182 (442), 22203 (2), 22206 (1), 22213 (7), 22302 (1), 22303 (789), 22306 (518), 22307 (1,208), 22310 (1,219), 22312 (454), 22315 (95)
APSec. 4101
Read from the use table: Table 4101.1, row "Construction Site Office and Storage", column "R-4", reads "AP". Sec. 4101.1 says: G. An “AP” in a cell of Table 4101.1 or Table 4101.2 indicates that the use is allowed only with approval of an administrative permit by the Zoning Administrator.
R-5 Varies
Depends: administrative permit, only if the use is a type or location that Sec. 4102.8.C(2) allows here and the use stays within the limits in Sec. 4102.8.C(1)
when the use is a type or location that Sec. 4102.8.C(2) allows here
Sec. 4102.8.C(2), Sec. 4102.8.C(1): The use must be located within the recorded subdivision that it serves or on the same lot where the construction project is located. … An administrative permit may be issued for a period beginning no earlier than 30 days before the commencement of actual construction and terminating no later than 20 days after completion of the last building to be constructed in the project.
11,400
no ZIP in the county's record (483), 20120 (118), 20121 (1,318), 20151 (497), 20170 (5), 22003 (541), 22015 (1,061), 22027 (107), 22031 (324), 22032 (473), 22033 (456), 22042 (69), 22043 (37), 22060 (1), 22079 (557), 22101 (111), 22124 (137), 22150 (246), 22151 (1), 22152 (617), 22153 (1,139), 22180 (59), 22181 (78), 22182 (121), 22303 (97), 22306 (811), 22307 (1), 22310 (237), 22312 (90), 22315 (1,608)
APSec. 4101
Read from the use table: Table 4101.1, row "Construction Site Office and Storage", column "R-5", reads "AP". Sec. 4101.1 says: G. An “AP” in a cell of Table 4101.1 or Table 4101.2 indicates that the use is allowed only with approval of an administrative permit by the Zoning Administrator.
R-8 Varies
Depends: administrative permit, only if the use is a type or location that Sec. 4102.8.C(2) allows here and the use stays within the limits in Sec. 4102.8.C(1)
when the use is a type or location that Sec. 4102.8.C(2) allows here
Sec. 4102.8.C(2), Sec. 4102.8.C(1): The use must be located within the recorded subdivision that it serves or on the same lot where the construction project is located. … An administrative permit may be issued for a period beginning no earlier than 30 days before the commencement of actual construction and terminating no later than 20 days after completion of the last building to be constructed in the project.
21,478
no ZIP in the county's record (600), 20120 (1,731), 20121 (2,235), 20151 (539), 20170 (798), 20191 (165), 22003 (332), 22015 (791), 22030 (220), 22031 (1,009), 22032 (1,164), 22033 (344), 22041 (79), 22042 (51), 22043 (719), 22044 (58), 22079 (1,321), 22101 (586), 22102 (178), 22124 (124), 22150 (471), 22151 (295), 22152 (943), 22153 (640), 22180 (83), 22181 (726), 22182 (299), 22303 (1,167), 22306 (402), 22307 (638), 22309 (695), 22310 (1,440), 22312 (169), 22315 (466)
APSec. 4101
Read from the use table: Table 4101.1, row "Construction Site Office and Storage", column "R-8", reads "AP". Sec. 4101.1 says: G. An “AP” in a cell of Table 4101.1 or Table 4101.2 indicates that the use is allowed only with approval of an administrative permit by the Zoning Administrator.
R-C Varies
Depends: administrative permit, only if the use is a type or location that Sec. 4102.8.C(2) allows here and the use stays within the limits in Sec. 4102.8.C(1)
when the use is a type or location that Sec. 4102.8.C(2) allows here
Sec. 4102.8.C(2), Sec. 4102.8.C(1): The use must be located within the recorded subdivision that it serves or on the same lot where the construction project is located. … An administrative permit may be issued for a period beginning no earlier than 30 days before the commencement of actual construction and terminating no later than 20 days after completion of the last building to be constructed in the project.
9,951
no ZIP in the county's record (645), 20120 (1,984), 20121 (425), 20124 (1,843), 20151 (577), 20152 (1), 22030 (1,696), 22039 (2,775), 22060 (2), 22079 (3)
APSec. 4101
Read from the use table: Table 4101.1, row "Construction Site Office and Storage", column "R-C", reads "AP". Sec. 4101.1 says: G. An “AP” in a cell of Table 4101.1 or Table 4101.2 indicates that the use is allowed only with approval of an administrative permit by the Zoning Administrator.
R-E Varies
Depends: administrative permit, only if the use is a type or location that Sec. 4102.8.C(2) allows here and the use stays within the limits in Sec. 4102.8.C(1)
when the use is a type or location that Sec. 4102.8.C(2) allows here
Sec. 4102.8.C(2), Sec. 4102.8.C(1): The use must be located within the recorded subdivision that it serves or on the same lot where the construction project is located. … An administrative permit may be issued for a period beginning no earlier than 30 days before the commencement of actual construction and terminating no later than 20 days after completion of the last building to be constructed in the project.
7,380
no ZIP in the county's record (1,087), 20171 (8), 20190 (47), 20191 (68), 20194 (1), 20195 (1), 22039 (5), 22066 (3,320), 22079 (1,082), 22101 (4), 22102 (639), 22124 (340), 22181 (424), 22182 (353), 22308 (1)
APSec. 4101
Read from the use table: Table 4101.1, row "Construction Site Office and Storage", column "R-E", reads "AP". Sec. 4101.1 says: G. An “AP” in a cell of Table 4101.1 or Table 4101.2 indicates that the use is allowed only with approval of an administrative permit by the Zoning Administrator.
R-MHP Varies
Depends: administrative permit, only if the use is a type or location that Sec. 4102.8.C(2) allows here and the use stays within the limits in Sec. 4102.8.C(1)
when the use is a type or location that Sec. 4102.8.C(2) allows here
Sec. 4102.8.C(2), Sec. 4102.8.C(1): The use must be located within the recorded subdivision that it serves or on the same lot where the construction project is located. … An administrative permit may be issued for a period beginning no earlier than 30 days before the commencement of actual construction and terminating no later than 20 days after completion of the last building to be constructed in the project.
2
22030 (1), 22306 (1)
APSec. 4101
Read from the use table: Table 4101.1, row "Construction Site Office and Storage", column "R-MHP", reads "AP". Sec. 4101.1 says: G. An “AP” in a cell of Table 4101.1 or Table 4101.2 indicates that the use is allowed only with approval of an administrative permit by the Zoning Administrator.

Pro and reports for Fairfax County, VA are coming soon.

Notify me when Fairfax County, VA launches

We use this email only to tell you when Fairfax County, VA launches. We never share it.

This answer is good through July 1, 2026 — that is the date the ordinance we hold runs to, as published by Fairfax County. We last checked with the county on September 14, 2026 and found nothing newer. That is a check on that date, not a promise about today.

What this does not cover

Built from scripts/build_reverse_index.py, generated 2026-10-11T20:59:04+00:00.