“data center” is Zonescore's word, not the ordinance's. This ordinance never uses it. The term it uses is Data Center, and that is the term cited and quoted below. We matched them because the ordinance defines Data Center as:

Data Center shall mean a use involving a building/premise in which the majority of the use is occupied by computers and/or telecommunications and related equipment

Sec. 32-100 -- Data Center

“data center” is Zonescore's word, not the ordinance's. This ordinance never uses it. The term it uses is Data Center outside the Data Center Opportunity Zone Overlay District, and that is the term cited and quoted below. We matched them because the ordinance defines Data Center outside the Data Center Opportunity Zone Overlay District as:

Data Center shall mean a use involving a building/premise in which the majority of the use is occupied by computers and/or telecommunications and related equipment

Sec. 32-100 -- Data Center

“data center” is Zonescore's word, not the ordinance's. This ordinance never uses it. The term it uses is Data Center within the Data Center Opportunity Zone Overlay District, and that is the term cited and quoted below. We matched them because the ordinance defines Data Center within the Data Center Opportunity Zone Overlay District as:

Data Center shall mean a use involving a building/premise in which the majority of the use is occupied by computers and/or telecommunications and related equipment

Sec. 32-100 -- Data Center

“data center” is Zonescore's word, not the ordinance's. This ordinance never uses it. The term it uses is Small Urban Data Center outside the Data Center Opportunity Zone Overlay District, and that is the term cited and quoted below. We matched them because the ordinance defines Small Urban Data Center outside the Data Center Opportunity Zone Overlay District as:

Data Center shall mean a use involving a building/premise in which the majority of the use is occupied by computers and/or telecommunications and related equipment

Sec. 32-100 -- Data Center

“data center” matches 4 uses this ordinance names separately. We do not choose between them — they can have different answers, so every one is shown.

Data Center

Allowed only with a discretionary approval in 1 district

These require a hearing or an approval from the county. They are not a “no”, and they are not a “yes” either.

DistrictProperties loadedCodeWhat says so
B-1
the ordinance paragraph quoted here
2,146
no ZIP in the county's record (65), 20109 (498), 20110 (29), 20111 (203), 20112 (68), 20136 (9), 20155 (180), 20169 (10), 20181 (55), 22025 (37), 22026 (35), 22172 (160), 22191 (415), 22192 (368), 22193 (14)
ConditionalSec. 32-401.13 item 10
Data Center.

Data Center outside the Data Center Opportunity Zone Overlay District

Allowed only with a discretionary approval in 7 districts

These require a hearing or an approval from the county. They are not a “no”, and they are not a “yes” either.

DistrictProperties loadedCodeWhat says so
M-1
the ordinance paragraph quoted here
856
no ZIP in the county's record (38), 20109 (496), 20110 (33), 20111 (4), 20112 (2), 20119 (3), 20136 (31), 20155 (107), 20169 (1), 20181 (2), 22026 (6), 22172 (1), 22191 (119), 22192 (13)
ConditionalSec. 32-403.13 item 3
Data Center outside the Data Center Opportunity Zone Overlay District.
M-2
the ordinance paragraph quoted here
411
no ZIP in the county's record (17), 20109 (233), 20110 (20), 20111 (1), 20112 (11), 20136 (23), 20155 (3), 20169 (5), 20181 (2), 22025 (2), 22026 (6), 22191 (34), 22192 (54)
ConditionalSec. 32-403.23 item 3
Data Center outside the Data Center Opportunity Zone Overlay District.
M/T
the ordinance paragraph quoted here
85
no ZIP in the county's record (5), 20109 (53), 20112 (10), 20136 (14), 20155 (3)
ConditionalSec. 32-403.33 item 3
Data Center outside the Data Center Opportunity Zone Overlay District.
O(F)
the ordinance paragraph quoted here
4
20109 (1), 22192 (3)
ConditionalSec. 32-402.43 item 3
Data Center outside the Data Center Opportunity Zone Overlay District.
O(H)
the ordinance paragraph quoted here
62
no ZIP in the county's record (2), 20109 (3), 20110 (1), 22191 (55), 22192 (1)
ConditionalSec. 32-402.23 item 3
Data Center outside the Data Center Opportunity Zone Overlay District.
O(L)
the ordinance paragraph quoted here
297
20109 (2), 20110 (46), 20111 (1), 20112 (2), 20136 (1), 20155 (1), 22191 (137), 22192 (90), 22193 (17)
ConditionalSec. 32-402.13 item 4
Data Center outside the Data Center Opportunity Zone Overlay District.
O(M)
the ordinance paragraph quoted here
25
20109 (1), 20112 (1), 20155 (6), 20169 (5), 22191 (2), 22192 (10)
ConditionalSec. 32-402.33 item 3
Data Center outside the Data Center Opportunity Zone Overlay District.

Data Center within the Data Center Opportunity Zone Overlay District

Allowed by right in 7 districts

DistrictProperties loadedCodeWhat says so
M-1
the ordinance paragraph quoted here
856
no ZIP in the county's record (38), 20109 (496), 20110 (33), 20111 (4), 20112 (2), 20119 (3), 20136 (31), 20155 (107), 20169 (1), 20181 (2), 22026 (6), 22172 (1), 22191 (119), 22192 (13)
AllowedSec. 32-403.11 item 19
Data Center within the Data Center Opportunity Zone Overlay District.
M-2
the ordinance paragraph quoted here
411
no ZIP in the county's record (17), 20109 (233), 20110 (20), 20111 (1), 20112 (11), 20136 (23), 20155 (3), 20169 (5), 20181 (2), 22025 (2), 22026 (6), 22191 (34), 22192 (54)
AllowedSec. 32-403.21 item 13
Data Center within the Data Center Opportunity Zone Overlay District.
M/T
the ordinance paragraph quoted here
85
no ZIP in the county's record (5), 20109 (53), 20112 (10), 20136 (14), 20155 (3)
AllowedSec. 32-403.31 item 21
Data Center within the Data Center Opportunity Zone Overlay District.
O(F)
the ordinance paragraph quoted here
4
20109 (1), 22192 (3)
AllowedSec. 32-402.41 item 8
Data Center within the Data Center Opportunity Zone Overlay District.
O(H)
the ordinance paragraph quoted here
62
no ZIP in the county's record (2), 20109 (3), 20110 (1), 22191 (55), 22192 (1)
AllowedSec. 32-402.21 item 6
Data Center within the Data Center Opportunity Zone Overlay District.
O(L)
the ordinance paragraph quoted here
297
20109 (2), 20110 (46), 20111 (1), 20112 (2), 20136 (1), 20155 (1), 22191 (137), 22192 (90), 22193 (17)
AllowedSec. 32-402.11 item 6
Data Center within the Data Center Opportunity Zone Overlay District.
O(M)
the ordinance paragraph quoted here
25
20109 (1), 20112 (1), 20155 (6), 20169 (5), 22191 (2), 22192 (10)
AllowedSec. 32-402.31 item 6
Data Center within the Data Center Opportunity Zone Overlay District.

Small Urban Data Center outside the Data Center Opportunity Zone Overlay District

Allowed only with a discretionary approval in 1 district

These require a hearing or an approval from the county. They are not a “no”, and they are not a “yes” either.

DistrictProperties loadedCodeWhat says so
MXD-U
the ordinance paragraph quoted here
4
20109 (4)
ConditionalSec. 32-307.33 item 17
Small Urban Data Center outside the Data Center Opportunity Zone Overlay District.

This part is the paid tier: the property list behind these counts. Everything above it on this page is free and carries the ordinance section and quote it came from.

Cancel anytime. You keep access until the end of the month you paid for. Access is remembered in this browser on this device only — there are no accounts, so opening a different browser will not carry it over. Lost it? Email us and we will re-issue.

This answer is good through September 9, 2025 — that is the date the ordinance we hold runs to, as published by Municode (Prince William County Code). We last checked with the county on September 24, 2026 and found nothing newer. That is a check on that date, not a promise about today.

What this does not cover

Built from scripts/build_reverse_index.py, generated 2026-10-11T20:59:04+00:00.